Asda – Counter Replacement

  • Client: ASDA
  • Location: Nationwide
  • Service: Programme Management | Client Agent | Installation
  • Duration: 30 Months
  •  

Following ASDA’s decision to removal all fish and meat counters across the estate, we were set the task to project manage the removal of the counters and implement a temporary solution until new concessionaires were agreed.

Once removed and ASDA partners agreed, Onyx project managed the installation of the new offers, these projects required working within existing space created by the removal of the fish and meat counters and in some cases reworking the existing counter line (Pizza and Rotis) or adding additional chilled and ambient space.

During 2020 and 2021 we completed the following:

  • 288 temp solutions
  • 65 Panku
  • 34 Sushi Daily
  • 8 Sticks Bowls and Rolls
  • 7 Cake Box
  • 5 Greggs
  • 4 House of Yum
  • 3 Kulaba
  • 2 BamTuk counters
  • 1 Upgraded ASDA offer
  • The scope of works included:

  • Programme Management
  • Project Phasing
  • Agreeing Specifications
  • Equipment quote requests
  • Management of client nominated sub-contractors
  • Project Team Liaison
  • Shop floor Fixture Installation
  • Cost control



  • Asda – Self Checkout Operations (SCO) Upgrade

    • Client: ASDA
    • Location: Nationwide
    • Service: Programme Management | Installation
    • Duration: 63 weeks
    •  

    A nationwide programme to transform the self-scan zones.

    This project required the contractors to work in a live environment with added covid restrictions, always keeping contractors and our client’s staff safe.
    The 2020 SCO project ran over 23 weeks, covering 230 stores.

    The 2021 SCO Project was larger, running over 40 weeks, covering 360 stores.

    We also took on some additional works installing new Lion tills into kiosks in 12 stores.

    The scope of works included:

  • Order Raising
  • Project Team Liaison
  • Snag Reporting
  • Budget Management



  • Morrisons – Reset & Café

    • Client: Morrisons
    • Location: Morley, West Yorkshire
    • Service: Fixture Management | Procurement | Installation
    • Duration: 5 weeks
    •  

    The project required us to work in a live trading store ensuring the store was ready for customers arriving from 7am every morning, whilst maintaining full product range throughout the duration of the scheme.

    The scheme was planned at five weeks and all phases were landed as per programme.

    The scope of works included:

  • Salesfloor fixture and commodity relay
  • Formation of new community room
  • Removal of existing security room and cig bunker
  • Formation of new Brew offer
  • Refurbishment of staff areas
  • Full refurbishment of customer café to current spec
  • Installation of new roll in milk cases



  • Asda – Refresh

    • Client: Asda
    • Location: Linwood, Scotland
    • Service: Fixture Management | Procurement | Installation
    •  

    Onyx were appointed directly by Asda to manage fixture and fittings packages as part of their national rollout programme.

    The scope of works included:

  • Programme management
  • Floor phasing
  • Equipment and order raising
  • Management of client nominated subcontractors
  • Project team liaison
  • Shopfloor fixture installation
  • Cost control



  • Kelly Deli – Bam Tuk Counter

    • Client: Kelly Deli, in association with ASDA
    • Location: ASDA, Minworth
    • Service: Project Management | Design Support | Client Agent
    •  

    Acting as Client Agent for ASDA, and working with Kelly Deli, ONYX overseen the installation of the first ever Bam Tuk counter in the UK.

    The scope of works included:

  • Programme Management
  • Project Phasing
  • Agreeing Specifications
  • Equipment and Order raising
  • Management of client nominated sub-contractors
  • Project Team Liaison
  • Shop floor Fixture Installation
  • Cost control



  • Boots – Seasonal POS Installations

    • Client: Boots
    • Location: Nationwide
    • Service: Programme Management | Installation
    •  

    ONYX were appointed by Boots in association with our logistics partners to provide installation support in the estate’s larger stores nationwide with a Seasonal POS rollout.

    The scope of works included:

  • Programme Management
  • Logistics liaison
  • Installation
  • Client Reporting



  • Greggs – New Concessions

    • Client: ASDA/Greggs
    • Location: Nationwide
    • Service: Programme Management | Client Agent
    •  

    Acting as Client Agent for ASDA, and working with Greggs, ONYX have overseen the installation of the first 5 instore Greggs counters within the ASDA Estate.

    The scope of works included:

  • Programme Management
  • Management of appointed Main Contractor & suppliers
  • Liaison with Greggs
  • Liaison between designers, contractors and suppliers
  • Cost Control